9. Checks to be performed before start-up
9.1
Tightening of all the electrical connections.
9.2
Levelling and verifying of the solidity of the support base.
9.3
Securing of the panels.
9.4
Verification of spaces for maintenance.
9.5
Correspondence of the supply voltage to the plate data.
9.6
Freedom of movement of the blades of the fans.
9.7
The absence of fluid leaks.
9.8
Removal of the protective film from the casing.
9.9
Checking of the cleanliness of the installation area.
9.10 Check that there are no foreign bodies in the vicinity of the fans and of the unit to avoid them being sucked in
by the fans.
9.11 Checking of the pressure tightness of the unit.
9.12 The unit is ready for use after all the instructions and warnings concerning the electrical connections and the
fluids have been strictly adhered to.
10. Checks to be performed after start-up
10.1 Initial start-up must take place under the supervision of a qualified technician.
10.2 Check the rotation direction of the motor fans. Contrary rotation could affect the performance of the model.
10.3 Check freedom of rotation of the impeller, without rubbing or irregular movements.
10.4 Check the movement of the fluid.
10.5 The absence of vibrations or unusual noises.
10.6 Check that the electric absorption is correct, in any case not exceeding what is reported in the label of the motor
fan.
10.7 Checking of correct tightening of the screws (Ref. EN 1090-2).