6556042.book Seite 20 Freitag, 15. April 2016 3:13 15
4 Preparation
20
4
Preparation
4.1
Initial start-up and longer breaks in use
✔ The turbine is only able to reach full power if indicated operating
Turbine
pressures are set [ → 15]. If necessary have the pressures checked
by a service engineer with a star tester that is placed between the
supply hose and the quick coupling.
➢ Sterilize the turbine and accessory parts prior to startup.
➢ Clean and maintain the turbine after longer breaks in use.
4.2
Prior to starting the work day
➢ Purge the water and air channels for 30 seconds.
4.3
Before each patient
1. Purge the water and air channels for 30 seconds.
Preparation _ Turbine
2. Attach the turbine [ → 22].
Operating Instructions BA ULTIMATE POWER+
65 56 042 D3560.201.08.02.02