404-1 System, Distributing Pro-Joining-Measuring Pro-Sorting Inline – Operating instructions
12.5 Establishing 1-bit communication links
The communication lines for use within the system are shipped loose and have to be plugged in.
Communication connections between the stations have to be set up in accordance with the following
example. The example has been kept general but it is applicable for all stations. Any deviations from this
standard will be pointed out.
Example with I/O plug connections between control consoles: connect the Q4 and GND sockets of the downstream station to the I6 and
GND sockets of the upstream station.
All components, tubing connections and cabling are clearly identified, so that all of the connections can be
readily restored.
12.6 Workstation
You will require the following items in order to commission the MPS system with the sample programs:
•
Dust-free laboratory environment
•
Compressed air supply: 600 kPa (6 bar)
•
A PC with installed PLC programming software