Installation
Chemical injection Supply
NOTES
System
(Continued)
208-240 Volt 60 Hz 3φ 3-Wire Models
Figure 2–9
Control Function Test
The machine should be cleaned after
the installation is complete. A function test
should then be executed on the unloaded
machine:
1. Check the power supply for such
characteristics as correct voltage, phase,
and cycles to be certain they are correct for
the machine.
2. Open manual shut-off valves to
the machine.
3. Turn on electric power.