Completing Installation of the GRAFIK Eye
1. Mount the control unit in the wallbox as
shown using the four screws pro vid ed.
Note: Follow all local and national
electrical codes when installing PELV
(Class 2: USA) wiring with line voltage/
mains wiring.
2. Verify installation:
• Restore power.
• Press the top scene button. The LED will
light.
• Press the zone raise or lower button.
Make sure the control unit is dimming all
connected loads.
3. Apply the protective overlay to the control
unit. See the complete installation and
operation guide at www.lutron.com for
instructions for naming zones.
Protective overlay
(apply after installation)
®
QS with DALI
®
For additional information, see the complete installation and operation guide at www.lutron.com/qs
GRAFIK Eye
7,9 in
(200 mm)
3,5 in
(87 mm)
3,75 in
(95 mm)
Note: When tightening mounting
screws, make sure that the hinged
cover and faceplate will open fully,
as shown.
QS with DALI Quick Installation and Operation Guide 8
®