Once all the blocks are positioned, the system is
fully wrapped in geo textile. This prevents the in-
gress of dirt particles into the system.
Please note:
There is an increased risk of slipping on EcoBloc Inspect system in frosty and wet conditions.
7.4
Fitting inlet
On the inlet surface, an X is cut into the geo textile.
The inlet pipe is slid in around 20 cm and the rest
of the X cut glued or welded to the pipe.
The vents needed are produced in the same way.
The vertically aligned vents can be produced on
the horizontal drill surface using a 90° KG bend.
7.5
Connecting inspection channel
The bases of the EcoBloc Inspect system can be
inspected and driven on. Please use the bottom
connections in the end plates of the EcoBloc In-
spect to connect the inspection channel
7. Installation