OPERATING PROGRAMME
NORMAL OPERATION
P
TL
t
2
t
1
M
M
I
V1
V2
SO
LED
Flame loss during operation (Recycle max 3 attempts)
MV = still
SO
LED
OPERATING TIMES (in seconds)
t1, t3l, t4l, t4a
t2l
max
max
1
30
Standby time pending an input signal to control box:
t1
reaction time, the control box stands still for the time t1.
Flame or flame simulation detected before demand for
t1I
heat: the appliance stands still.
Wait time after a request for heat:
t2
the control box stays still for the t2 time.
Check whether the air pressure switch has already been
moved to the work position before the required heat:
t2a
the control box remains in standby status, a lockout fol-
lows if the air pressure switch remains switched for the
T2a time.
Flame or flame simulation detected before during
standby time:
t2I
lockout occurs if flame or flame simulation persists for
time t2l.
Pre-purging time:
t3
start of the fan motor.
Time for checking the switching of the air pressure
switch in the operating position during the pre-purging
t3a
time: if the pressure switch does not switch within t3a
a lockout follows.
Flame or flame simulation detected during pre-purging:
t3I
immediate lockout.
3312
t
3
t
4i
t
s
t5
Green
Green
t2, t4i
t2a
t3
-
-
-
max
3
120
40
KEY TO LAY-OUT
I
LED – Reset button LED indicating operating
M
SO – Ionisation probe
TL – Limit thermostat
V1 – Gas valve 1
V2 – Gas valve 2
t
4L
.
Lockout
D7397
t3a
t3r
ts
t5
max
-
min/max max
15
70
3
5/25
A recycle attempt is made in the event of a pressure
drop during pre-ventilation: in the case of a second air
pressure drop between the 16th and 29th second
t3r
another lockout follows; if there is a pressure drop
between the 30th second and 40th second , the appli-
ance immediately goes into lockout.
Safety time:
ts
if at the end of the ts time there is no flame, a block fol-
lows.
Air pressure drop checking time during the ts time and
t4a
the normal operation:
the control box locks out immediately.
Transformer turn on time:
t4i
total ignition time.
Flame loss in operation:
t4I
valve drop maximum reaction time, lockout occurs after
3 recycle attempts.
Delay time between the 1
nd
t5
2
stage valve opening time after the 1
opening.
Post-purging time:
t6
additional purging time on the opening of the heat limit
thermostat (TL).
9
GB
– Ignition transformer
status
– Fan motor
st
stage
nd
stage
Red (LED lights)
Green (LED lights)
No signal needs to be received
t6
360
st
nd
and 2
stage:
st
stage valve