Descargar Imprimir esta página

Commissioning, Operation - WIKA LSO.25 Manual De Instrucciones

Publicidad

Idiomas disponibles

Idiomas disponibles

6. Commissioning, operation

6. Commissioning, operation
Before the installation a check of the function can be carried out. The device attached
GB
provisionally and the glass tip are one and from dived to this for the test in a glass with
liquid (adjustment if necessary, see chapter "7.2 Adjustment with CAL").
WARNING!
The electrical connection only be carried out by qualified skilled personnel.
Observe the appropriate VDE regulations.
6.1 Installation instructions transducer model LSO.06
The sensors may be installed in any direction, i. e. from top, bottom, sideways or inclined.
In some special applications it is recommended to use following hints:
High viscosity:
Dry Running protection for pumps:
Overfill prevention devices:
Vertical installation
20
sideways or from bottom
if the pipes to or from the pump are installed
horizontally use top mounting for fast detection of
liquid
usually vertically from above
Installation model LSO.06 from top with flange
connection e. g. as overflow control.
Insertion length EL from sealing face flange
DIN flanges from DN25 PN6
ANSI flanges
The sealing forms are freely selectable
Explosion-protected version:
Flanges seal-welded with the transducer
sensor component
If seal-welded: no hexagon on sensor
component
WIKA operating instructions models LSO.06, LSO.25

Publicidad

loading

Productos relacionados para WIKA LSO.25

Este manual también es adecuado para:

Lso.06