Drop-In Installation - Jacuzzi COMFORT PURE AIR Serie Instalación Y Operación De Instrucciones

Tabla de contenido

Publicidad

Idiomas disponibles

Idiomas disponibles

Comfort Pure Air™ Bath

Drop-in Installation

Before you begin your installation, please read the following:
Observe all local and building codes.
Determine which tools will be used during the installation.
Additional bathtub drain parts and plumbing are commercially available at plumbing and hardware stores.
Drain/Overflow rough-in information is included with your bathtub in the installation instruction manual.
Complete the bathtub surround installation.
Install drain/overflow according to the manufacturer's
1
instructions. Refer also to the Technical
Specifications Manual.
Watertight installation of the drain is the installer's
responsibility. Drain leakage is excluded from the
Jacuzzi Luxury Bath warranty of this product.
Install the faucet at this time. It is recommended that
2
the faucet be installed by a qualified plumber.
Proper installation of the spout plumbing and
compliance with local codes are the responsibility
of the installer. Jacuzzi Luxury Bath does not
warrant connections of water supply fittings and
piping, fill systems, or drain/overflow systems. Nor
is it responsible for damage to the bathtub which
may occur during installation.
A non-flammable protective barrier must be
placed between the soldering work and the
bathtub unit to prevent damage to the bathtub.
Prepare the cut-out hole for the bathtub using
3
either the provided template or the cutout
dimensions listed in the specifications table in the
Technical Specifications Manual.
The template may show guides for more than one
bathtub, be certain to select the appropriate guide
lines. If under mounting is an option, be careful to
select the guide lines that apply to the installation
that you are performing.
Complete all deck finish work. Cover to protect
4
from damaging while placing the bathtub.
Insulation may be placed within the bathtub
5
surround.
Provide adequate ventilation around the motor/
pump to ensure sufficient airflow and cooling.
Turn off power supply to dedicated GFCI
6
protected circuits.
Place a piece of scrap lumber on each of the ends
7
of the cutout – this will be used as a temporary
support prior to lowering the bathtub fully into the
opening.
Connect flex water supply lines to faucet and plug
8
power cords into GFCI outlets.
DO NOT use plumbing fixtures or lines to lower
the unit. Allow the bathtub to rest on the supports.
Installation and Operation
Tile
Subfloor
Mortar or
Adhesive
Flashing
Tile or Finished
Surface
Level Subfloor
www.jacuzzi.com
Sealant
1˝ x 4˝
(25mm x 101mm)
Exploded View
Not For Support
Figure 5
Support Member
Level Subfloor
Figure 6
Scrap Lumber
Tile or
Finished
Surface
Blower
Member Support
Figure 7
Blower
Scrap Lumber
Page 11

Publicidad

Tabla de contenido

Solución de problemas

loading