Leveling:
the level precision of the machine is a precondition of the precise detection for four-wheel alignment, and therefore
the machine leveling is significant
1 ) Lift the main lift platform to the fifth or sixth gear, then press the "Lock" button to fasten the safety jaws of the
left and right platforms into the safety gear racks firmly
2) Inspect that the surfaces of the left and right platforms are level laterally and longitudinally with a transparent
leveling pipe or level gauge(Fig. 41)
3) If the platforms are of unequal heights due to an uneven foundation, adjust the adjusting bolts(Fig. 42) on the
base frame of the main lift with a wrench to make the platforms' level precision meet the detection requirements
of four-wheel alignment.
Fig. 42
4) After leveling, insert the central expansion screws of foundation bolts, and fix the expansion screws with a heavy
hammer.
5) Tighten the nuts of the foundation bolts.
6) If the concrete curing period is not over, do not hammer the central expansion screws of the foundation bolts.
After leveling, the clearance between the base frame and the ground must be filled with cement mortar.
Low position leveling:
when the main platform is lowered to the lowest position, the platform at the low position can be leveled by adjusting the
supporting screw rods at the bottom of the main platform (See Fig. 43)
1 ) Loosen the retraining nuts first
2) Adjust the length of the supporting screw rod to the proper position
3) Then tighten the nut