In the following diagram the leak test is carried out by using 2 auxiliary valves.
The MTC10 controls valves V3 and V4. The Burner Control controls valves V1 and V2.
The following checks are performed before starting the burner:
1. Leak test V1 and V3
2. Leak test V2 and V4
During the test, the gas can be discharged into the combustion chamber or, if this is not allowed, it must be released outside
in a safe place. Once the test is passed, the Burner Control opens V1 and V2.