INSTALLATION
Choosing a site
Installation must be done in accordance with any local regulations. When deciding on a position for the unit,
take care to allow for the cable lengths available. The power supply and electrolytic cell are very heavy. Allow
for this during installation. If any components are dropped, damage will occur. The electrolytic cell can be
plumbed in using 80mm (3"), or 50mm (2") size PVC pressure pipe.
The power supply box should be wall mounted using the brackets provided which are designed for masonry
bolts/wall plugs. The brackets provide a gap between the back of the unit and the wall for enough air flow.
The power supply box should be mounted approximately 1.2 – 1.5m (4ft - 5ft) above ground level.
Sample installation diagram
External
Controller
(ORP)
Pump
Suction Line
from Pool
Power
Source
External
Controller
Sampling
Point
Media
Filter
8
Note: Always fit the
cell so that the Gas
Sensor is on the outlet
side of the cell
Note: Cell must be
installed in a horizontal
position ONLY.
Cell Cable
Flow
Switch
Gas
Sensor
Connector
Cell
Sampling
Point
Return Line
to Pool