4 .3 Lifting of equipment
Before shipping, each air conditioner unit has been a rigorous inspection and testing, to ensure the quality and
performance of the unit, and therefore care must be taken during installation of the device, especially not
damage the control system and the pipeline.
During on-site installation, there are differences between the left and right in indoor, outdoor unit. With large
size or space restrictions in indoor, outdoor unit, and hard to carry, the way of lifting can be considered.
General requirements during lifting:
1. Inclination of outdoor unit should not exceed 20 degrees.
2. During lifting, force is applied to the device, the device must be separated from hoisting rope with a cloth or
other flexible objects to avoid damage to the device.
3. During lifting, the equipment must be carefully lifted or lowered, the force on the stress points of the device
must be uniform.
During lifting of the equipment, refer to the following methods:
1. Manual lifting, forklift lifting.
2. The device can also be moved using the methods of logs (or pipes), labor goes on and so on.
Fixation of equipment. After the completion of equipment lifting, the next step must be carried out:
1.
When the device is lifted onto the foundation, Equipment levelness is adjusted with a level meter, the
error does not exceed 0.1%.
2.
When the equipment is put down evenly, the device can be fixed, and the force exerted on the fasteners
must be uniform.