Initial Operation; Power Switch - ShenPaz Focus 4010 Manual De Instrucciones

Horno de cocción de porcelana
Tabla de contenido

Publicidad

Idiomas disponibles

Idiomas disponibles

3. Initial Operation

Before running any firing cycles the furnace must undergo an initial drying procedure to
remove any absorbed humidity that may have entered during transit.
The furnace firing procedure is a special drying cycle for the firing chamber, and it must be
carried out before you start using your furnace.
The procedure is mentioned here before the operating instructions, to remind you to read the
entire operations manual and then to run the initial firing procedure before working with any
program.
We highly recommend you to use a dry pump that is able to reach 720 mmHg within
35-40 sec
3.1
Initial Furnace firing for muffle drying
1) Connect the furnace as instructed previous sections.
2) Using the
3) Place the ceramic table on the furnace platform.
4) Use program No.1 (the BUILD-IN parameters listed below) :-
Table 3-1
5) Run program No.1
This program will dry the muffle from any absorbed humidity.
6) Repeat the above procedure 2 to 3 times.
5
3
m
REMEMBER:
Only after completing this procedure is the furnace ready for use.
3.2

Power Switch :

To start the furnace press the power switch located on the rear panel to the ON
position, the furnace is now in the Stand -by Mode.
By pressing the ON/OFF button on the front panel, the furnace is turned on. This mode is
called the Idle Mode. The temperature would rise and will maintain on 200ºC.
FOCUS 4010/HT Dental Porcelain Furnace
]
TSIL/POTS
[
key move the platform to the lowest position.
START TEMP
UP TIME
DRY TIME
HEAT RATE
HIGH TEMP
TEMP DELAY
5
m
40
C/m
500 C
3 minutes
(03:00)
1 minutes
(01:00)
40 C /minute
950 C
5 minutes
(05:00)
Page 10