SPECIFICATIONS
Power supply
Liquid temp. range
Discharge size
Sump basin
Switch on/off
Read this Owner's Manual for installation, operation, and safety information.
INSTALLATION
TYPICAL DEWATERING INSTALLATION (3/4 in. or less Solids)
Install pump on a hard, level surface (cement, asphalt, etc.). Never place pump directly on earth, clay or gravel surfaces.
1.
Piping must be 1-1/2 in. minimum to carry volume of pump discharge. Check local codes to determine if a check
valve is required in your system. In cold climates, check valves are not used to prevent effluent from freezing in
piping.
If using as a sump pump, a check valve is recommended.
2.
Use a 2 in. (5.1 cm) swing check valve in the pump discharge to prevent backflow of liquid into the sump basin.
The check valve should be a free flow valve that will easily pass solids.
For best performance of the check valve when handling solids, do not install it with the discharge angled more than 45° above the
horizontal. Do not install the check valve in a vertical position as solids may settle in the valve and prevent opening on start up.
3. Drill a 1/8" (3.2mm) hole in discharge pipe about 1"-2" (2.5 -5.1cm) above quick connector. The hole must be in the
sump.
4
115V, 60 HZ., 15 Amp Circuit
32-131°F (0-55°C)
2 in. FNPT
Minimum 18 in. (460 mm) diameter, 30 in. (760 mm) depth
On: 13.3 in. (338 mm), Off: 5 in. (127 mm)
For Professional Technical Support call 1-844-242-2475