Flow Chart - Abicor Binzel BRS-CC Instructivo De Servicio

Unidad de mantenimiento
Ocultar thumbs Ver también para BRS-CC:
Tabla de contenido

Publicidad

Idiomas disponibles

Idiomas disponibles

BRS-CC

5.9 Flow chart

Cleaning &
Injection
Fig. 11
Y1
Y2
Y3
Y4
Air-blast option
Ready
Tab. 14
Position P1
Approach
Determine cause
and eliminate it
No
Option
Air blast = 1
Waiting time
approx. 0.5 sec.
Waiting time
approx. 2 sec.
Option
Air blast = 0
Determine cause
No
and eliminate it
Flow chart
5/2 directional valve stroke UP - DOWN
5/2 directional valve for clamping cylinder (CLAMP - RELEASE) and for
compressed-air motor (ON - OFF)
5/2 directional valve for wire cutter (ON - OFF)
5/2 directional valve for injector (ON - OFF)
Air-blast through cable assembly (ON - OFF)
Home position of the cleaning station (stroke cylinder down, S1 activated)
Explanations
Position P3
Approach
Input
Ready = 1
Yes
Position P2
Approach
Output
Y2 = I
Output
Y1 = I
Output
Y1 = 0
Output
Y2 = 0
Input
Ready = 1
Yes
5 Putting into operation
Position P4
Approach
Output
Y4 = 1
Waiting time
approx. 1 sec.
Output
Y4 = 0
Position P3
Approach
Position P5
Approach
Output
Y3 = I
Waiting time
approx. 0.5 sec.
Output
Y3 = 0
Move out of
maintenance station
EN - 14

Publicidad

Tabla de contenido
loading

Tabla de contenido