7.2
Unpacking Large System of the LN 600, FP 200, FPV 100-200,
GL 20-30, TFS 1000, OEN 250/700 and DT Series
Systems of the FP210-215, FPV200-202, LN600 and OEN 250/700 series are delivered
without cardboard, secured on a pallet.
•
Firstly, set the pallet on a level, suitable surface.
•
Now loosen the belts and any other attached fastening aids.
•
Afterwards, remove the transparent foil and protective cardboard boxes.
•
Carefully lift the system from the pallet.
•
It is mandatory to observe the correct securing of the system to the load-fastening
equipment.
•
Caution! Depending on the size and weight of the system, have a sufficient number
of helpers available.
•
Dispose of the packaging in accordance with the applicable regulations.
Warning! Use only original TBH crane eyelets; observe enclosed safety
instructions!
7.3
Checking and Alignment of the Modules
TBH extraction and filter systems have a modular design. In general, they consist of a motor
module with control system, and one to three filter modules as well as a lid module.
For systems equipped with buckles/clasps, check the following after unpacking:
•
Are individual modules shifted against each other?
•
Are the toggle fasteners tensioned or loose? When being tensioned, the toggle
fasteners should press the corresponding seal approx. 2-4 mm together.
•
Pay attention not to press the toggle fasteners too excessively together, as this
could damage the seals.
•
Check all seals for damage such as scrapes, cracks, pressure marks or similar.
•
Check all differential-pressure nipples for damage such as breakage,
bending/kinking, blockage or similar.
7.4
Setting Up the System
•
Firstly, follow the steps in the section "Unpacking".
•
Set up the system on a clean, level surface (observe the information in section:
"Operating, Environmental, Storage and Transport Conditions")
•
The ambient air may not have a too high a dust load, as otherwise the turbine can
become soiled/contaminated via the bypass openings. Please contact your country
representative if in doubt.
•
Secure the system (e.g. apply the wheel/castor brake or affix the FP200 series to
the ground using forklift feet), please pay particular attention to the safe position of
the system when using superstructures with a large lever arm (e.g. extraction
elements installed on the systems) and install additional securing means (ground
anchors or similar) in case of doubt. Always observe the operating regulations at
the set-up location.
•
the ventilation slots of the bypass cooling system may not be covered off.
•
Connect the remote control cable to the interface, as required (see section 8)
•
For devices of the FPV series, the appropriately dimensioned extraction and filter
system must be connected downstream.
Installation and Starting of Operation
77