9. Start-up
procedure
(continuation)
10. Operation
Check the level of coolant in the circulating coolant unit.
Setting the level of shielding gas
Set the required gas volume at the pressure reducing valve. Type and quantity
of shield gas to be used depend on the welding task to be performed.
Checklist
– Check the cable assembly before connecting it to the wire feeding unit to see
whether the wire guide liner is suitable for the wire diameter and wire type.
– Check the equipment parts in the torch neck, whether the correct contact tip
and torch neck liner is being used for the wire diameter and wire type.
– Check the function of the cooled unit.
Changing wire
– When changing the wire, ensure that the end of the wire is deburred.
– Insert the wire into the wire feeding unit following the operating instructions.
– When inserting the wire, press the button powerless wire feeding on the wire
feeding unit.
Welding process
Before you start welding, you must check your protective equipment
and the surrounding area for possible dangers as outlined in
chapter 6.
Make sure that all the parameters required such as welding current,
wire feeding etc. are set on the power unit for MIG / MAG welding
and according to the requirements of your welding task.
For instructions and recommendations on the welding process itself (technique,
materials, heat...) please consult the relevant literature. This information is not to
be found in these operating instructions.
The torch neck must not be used as a chipping hammer!
Removing from service
When you have finished welding:
1. Wait until the inert gas post-flow time is over.
2. Switch off the power supply.
3. Close the shut-off-valve for the gas supply.