2.0 - TECHNICAL DATA

• Use
• Ambient temperature
• Supply voltages (see table 2)
• Power supply tolerance
• Electric wiring
• No. cycles/hour
• Absorbed power
• Maximum operating pressure
DN 15 - DN 20 - DN 25
DN 32 - DN 40 - DN 50
• Opening time
• Closing time
• Protection rating
• Class
• Mechanical resistance
• Rp Threaded connections
• Flanged connections to be coupled with PN 16 flanges : (DN 25** - DN 32 - DN 40 - DN 50) ISO 7005 / EN 1092-1
• NPT threaded or ANSI 150 flanged connections : on request
• Filter element
• In compliance with
* Only single-phase, the device does not work if powered with three-phase voltage.
** DN 25 with swivel flanges on request.

2.1 - MODEL IDENTIFICATION

EV-1
: Fast opening P. max 0.5 or 1 bar (see product label)
EV-3
: Fast opening P. max 3 bar
EV-6
: Fast opening P. max 6 bar
EVF-1
: Fast opening + flow adjustment P. max 0.5 or 1 bar (see product label)
EVF-3
: Fast opening + flow adjustment P. max 3 bar
EVF-6
: Fast opening + flow adjustment P. max 6 bar
2.2 - SIL LEVEL
The SIL level of the stand-alone solenoid valve is SIL 2; when two solenoids are installed in series and the relative leak test
(Valve Proving System), certified according to EN 1643, the achieved level is SIL 3, as set forth in EN 676:2008. The solenoid
valve has PL d level. For further data refer to the SIL LEVEL table (table 3).

3.0 - COMMISSIONING THE DEVICE

3.1 - OPERATIONS PRIOR TO INSTALLATION

• It is necessary to close the gas upstream of the valve prior to installation;
• Make sure that the line pressure DOES NOT EXCEED the maximum pressure declared on the product label;
• Any protective caps (if any) must be removed prior to installation;
• Valve pipes and insides must be clear of any foreign bodies;
If the device is threaded:
• make sure that the pipe thread is not too long, to prevent damaging the body of the device when screwing it on;
If the device is flanged:
• make sure the inlet and outlet counter-flanges are perfectly coaxial and parallel in order to prevent unnecessary
mechanical stress to the body. Also calculate the space to insert the seal gasket;
• With regard to tightening operations, equip yourself with one or two calibrated torque wrenches or other controlled locking
tools;
EV(F)-1-3-6
: non-aggressive gases of the three families (dry gases)
: -20 ÷ +60 °C
: 12 Vdc - 12 V/50 Hz - 24 Vdc - 24 V/50 Hz - 110 V/50-60 Hz - 230 V/50-60 Hz*
: -15% ... +10%
: cable gland M20x1.5
: see table 2a - 2b - 2c
: see table 2a - 2b - 2c
:
EV(F)-1 = 1 bar - EV(F)-3 = 3 bar - EV(F)-6 = 6 bar
EV(F)-1 = 0.5 or 1 bar (see product label)
: <1 s
: <1 s
: IP65
: A
: Group 2
: (DN 15 - DN 20 - DN 25 - DN 32 - DN 40 - DN 50) according to EN 10226
: 1 mm mesh piping (except EV(F)-3 - EV(F)-6)
: Regulation (EU) 2016/426 (Appliances burning gaseous fuels)
PED Directive 2014/68/EU (versions with P.max = 1-3-6 bar)
EMCDirective 2014/30/EU - LVD Directive 2014/35/EU
RoHS II Directive 2011/65/EU
10
Madas Technical Manual - 1|1.5a - REV. 0 of 10
May 2018
th