Insulation test
Isolationsprüfung
Insulation test, English – Isolationsprüfung, Deutsch
Each set must be insulation tested after having been dismantled. Make the test
when the set has been reassembled and is ready to be returned to the customer.
Flashovers must not occur during the testing procedure!
Make the insulation test as follows:
Short-circuit the two pins of the mains plug and connect them to one of the
terminals of the insulation tester. Connect the other terminal to ground on the
aerial socket.
NOTE!
To avoid damaging the set it is essential that both terminals of the insulation tester
have good contact.
Slowly turn the voltage control of the insulation tester until a voltage of 1.5 kV
and max. 10mA is obtained. Maintain that voltage for one second, then slowly
turn it down again.
Nach einer Zerlegung ist bei jedem Gerät eine Isolationsprüfung vorzunehmen.
Die Prüfung wird dann ausgeführt, wenn das Gerät wieder vollständig
zusammengebaut und zur Auslieferung an den Kunden bereit ist.
Überschläge dürfen während der Prüfung nicht vorkommen!
Die Isolationsprüfung in folgender Weise durchführen:
Die beiden Steckerstifte am Netzstecker kurzschließen und an eine der
Anschlußklemmen des Isolationsprüfers anschließen. Die andere Anschlußklemme
an die Masse des Antennenanschlußes anschließen.
ACHTUNG!
Um Beschädigungen des Gerätes zu vermeiden, ist es wichtig, daß beide
Anschlußklemmen des Isolations-prüfers einen sehr guten Kontakt haben.
Die Spannungsregelung des Isolationsprüfers langsam nach oben drehen, bis eine
Spannung von 1,5 kV und max. 10mA erreicht wird. Diese Einstellung 1 Sekund
aufrechterhalten, und anschließend die Spannung wieder langsam nach unten
drehen.