Before working on the machine it is advisable to follow the steps below:
1. Cut the machine voltage.
2. Block the starting-up mechanisms.
3. Check that there is no voltage in the circuits, including the auxiliaries and
supplementary services.
4. Wait until the wheel has stopped completely.
The mentioned list should be considered indicative and not binding, since there may
be specific safety rules within specific safety procedures.
Periodically control:
-
The mechanical parts are firmly secured and the machine support screws
are in good condition.
-
Correct positioning and fixing and the condition of the leading-in wires and
isolation components.
-
Machine and electric motor temperature. In case of irregularity, stop the
machine immediately and proceed with its repair.
-
Machine shake. In case of irregularity, stop the machine immediately and
proceed with its repair.
Because of the complexity of cases dealt with, the installation, use and maintenance
instructions in this manual do not intend to examine and deal with all possible
service and maintenance situations. If supplementary instructions are necessary or
if specific problems arise, do not hesitate to contact the machine distributor or the
manufacturer.

3. INSTALLATION AND ASSEMBLY

GENERAL
Assembly and installation of our pumps is only permitted in swimming pools or
tanks complying with regulation HD 384.7.702. In case of doubt please consult a
specialist.
All pumps come with a two-drill foot to allow for them to be fixed in the floor by
means of an anchor. (Fig. 1).