Descargar Imprimir esta página

Miele PDR 910 G Plano De Instalación página 43

Secadora industria
Ocultar thumbs Ver también para PDR 910 G:

Publicidad

Idiomas disponibles
  • MX

Idiomas disponibles

  • MEXICANO, página 83
Order of steps for
commissioning or
conversion work
 Risk of explosion if gas-heated tumble dryers have leaks.
Once the work has been completed, there is a risk that the gas-
heated tumble dryer may have a leak and gas may escape.
After completing any commissioning, maintenance, conversion or
repair work, check the tumble dryer for leaks. Particular attention
must be paid to the measurement connections on the gas valve.
Checks must be performed when the burner is both switched on
and switched off.
Check that the points listed in "Supply air and exhaust air manage-
ment" have been taken into consideration.
The steps below should be followed in the given order when commis-
sioning or converting the machine.
1.
Ask the gas supply company what the gas family, gas group
and connection pressure are. Compare this information with the
values specified on the machine (see data plate).
2.
Check and correct the factory-set jet pressure based on the
tables "Settings with natural gas" and "Settings with liquid gas".
3.
If the gas family, gas group or connection pressure is different, it
must be converted as instructed in the connection and conver-
sion instructions ("Setting and conversion instructions for gas").
You must then change the data plate.
Follow the accompanying setting and conversion instructions
when changing the gas family. If there is no setting and conver-
sion kit available, you can request one from the Miele Customer
Service Department. Please quote the following:
– the model
– the number of the tumble dryer
– the gas family
– the gas group
– the gas connection pressure
– the country where the machine has been installed
Set the jet pressure at the machine's gas regulating valve (see
"Settings with natural gas/liquid gas" section and the accom-
panying setting and conversion instructions).
4.
Switch on all gas consumers that are present, including the in-
stalled tumble dryer.
5.
Measure the connection pressure. The connection pressure
must correspond to the data plate information and the ac-
companying setting and conversion instructions.
en - Installation notes
43

Publicidad

loading