Finishing initial commissioning
8.8
Switching on the DC supply
Set the DC circuit breaker on the inverter to position I (Fig. 8).
After testing via the internal MSD (approx. 2 minutes), the power fed into the grid can be shown
on the display (assuming that sunlight is present).
Set the DC circuit breaker to position I.
Fig. 8:
744.711 | 12.20
11. Press to select a setting value for the first node. P %
has predefined fixed values for the first and last node
(000 %, 100 %).
12. Press SET briefly. The setting value flashes.
13. Press to change the value.
14. Press SET briefly. The change is adopted.
15. Repeat steps 11 to 14 for the other setting value.
16. Press SET for a longer time.
17. Repeat steps 11 to 16 for the setting values of the re-
maining nodes.
18. The characteristic curve is displayed graphically (example
in Fig. left).
19. Press SET for a longer time.
1. Press ESC to jump stepwise backwards and correct set-
tings or
press and hold SET for a longer period of time to finish
initial commissioning.
2. If SET was pressed for a longer time then the inverter
restarts anew and synchronises itself with the grid.
EN
23