Checkliste für die Erstinbetriebnahme
Lista di controllo per la messa in funzione
Checking list para la puesta en marcha
2
Checking the thermosiphon system installation
2.13 Make sure that the valves not isolate!
2.14 Do you checked the mounting system for visible damage?
2.15 Did a authorized electrican installed the original electrical heater?
2.16 Did you mount the thermosiphon system accordingly the manual?
2.17 Do you checked the mounting system for visible damage?
2.18 Are all connections done correctly? (screws are tighten etc.)
2.19 Are the tank fastening done correctly?
2.20
2.21 Did you do a functional check 30 minutes after installation (sun iradiation is necessary)?
Did you do a functional check 1 week after installation (sun iradiation is necessary)? Check of system
2.22
(screws, level of liquids, leakage, etc.)
2.23
Date
66
Signature installer, stamp
EN
30°
45°
yes
no