15.3.3 Physical installation

The SmartStart must be mounted within 1 m of the PSk2
controller. The provided SmartStart to PSk2 cable will define
a logical mounting position.
Bottom access is required to the SmartStart for the connec-
tion of cables. The battery and connections slide out of the
bottom of the SmartStart. You must allow a space above
and below the SmartStart of 250 mm. If you are using
trunking, then ensure that you have access to both the top
and bottom wall mounting holes and the 4 bottom case
screws so that the SmartStart can be lifted for access to
terminals and the battery.
Figure 61: SmartStart overview
board
space for
battery
battery
fixation
pin

15.3.4 Cable entries and external sockets

There are cable glands and plug sockets in the bottom of
the SmartStart. The socket for the remote PSk2 connection
is pre-wired and pre-assembled in the SmartStart housing.
Cables for the generator connection and the ancillary
connection which lead through the cable glands have to be
fixed tightly in the glands for strain relief and sealing.