Tabla de contenido

Publicidad

Idiomas disponibles
  • MX

Idiomas disponibles

4.2

Installation

1. Move the machine (and the accessories) to its final location.
Note:
Allow ample working space. See Figure 8.
Figure 8: Working space.
L = Maximum board length, S = Minimum space 60 cm (24 in.).
2. Turn down the four leveling feet until the castors are off the floor.
3. Remove all transport material.
Remove the straps holding the control panel arm
Cut the straps around the shaft suspensions and remove the foam pads.
Cut the straps holding the in-feed table arms
Cut the straps around the main roller axis and move up the top main roller to
remove the transport blocks from the nip.
Cut the straps holding the upper pull roller and open the pull rollers to remove the
transport plates.
4. Put a spirit level on the upper main roller and level the machine by adjusting the four
leveling feet.
CAUTION:
Check the mains values before connecting. See section 3.4 for power supply
details.
5. Connect the machine to the mains using the power cable supplied with the machine.
CAUTION:
Only if absolutely necessary, use an extension cable of ample capacity.
Unroll the extension cable completely.
WARNING:
MAKE SURE THE POWER SUPPLY CABLE AND/OR THE EXTENSION
CABLE IS NOT BLOCKING YOUR WAY AROUND THE MACHINE.
20
User Manual 80Pro

Publicidad

Tabla de contenido
loading

Tabla de contenido