7.3. Installation of the guard
GB
trac™ guardrail
The installer should proceed as follows:
Step 1:
Clear the installation area on which the guard
trac™ or guard trac™ plus guardrail is to be
installed.
Step 2:
Clean the cleared area using appropriate
resources. After cleaning, the surface must be
free of all dirt such as dust, oil, grease, mould,
algae, moss, leaves or other.
7.3.1. Barrier (fg.18)
1.
Set up the fully equipped double bracket:
Each support is equipped with an anti-slip
pad (rep.1 fg.7) at the end to avoid any risk
of deterioration of the roof sealant.
However, it is recommended that the
installer place it gently on the ground and
not to step on it, which could lead to the
deterioration of the roof sealant. Space
the supports L1= 3076 mm (fg.18.1)
apart at a minimum distance of 50mm
from the parapet.
2.
Place a latch on each double bracket
(rep.1, fg.18.2)
3.
Insert the barrier into the holes in the
double bracket (fg.18.3)
DANGER: the gearwheel must be
enmeshed with the latch and be in
contact with the upper surface of the
latch and the upper surface of the double
bracket tubes (see detail B of Fig. 18.3).
4.
Take a first counterweight with two hands
at the clearances and position it on the
first double bracket (rep. 2, fig. 18.4),
taking care to place the double bracket
arm in the counterweight groove provided
to receive it.
IMPORTANT:
concrete counterweight on the bracket,
the installer must ensure that the
installation surface Sm of the counterweight
block (fig. 6) does not present any sharp edges,
deterioration or foreign body to deteriorate the
roof sealant of the roof.
14
Before
placing
the
NOTE:
counterweight (fg.22), bring it
against the hook of the double
bracket (step 1), swivel the weight (step 2), and
settle it (step3).
IMPORTANT:
counterweight check that it is laying
against the whole installation area Sm
(Fig. 6) and is secured by the front and rear
hooks of the double bracket.
5.
The first weight is placed
6.
Do the same for the other counterweight
rep. 3 fig 18.5
7.
Do the same for the other counterweight
rep. 4 fig 18.6
8.
Do the same for the other counterweight
rep. 5 fig 18.7
The guard trac™ guardrail is installed. Do the
same for the adjacent barriers.
NOTE: The assembly of the
barriers adapts to the shape of
the area to be cordoned off
thanks to the gearwheel system of the barriers
and the latch. The permissible angles are shown
in the table below (fig. 21):
Barrier
Installation angles
3m
guard
Amin= 30° to Amax=
trac™ barrier
330° by steps of 30°
Long
Amin= 30° to Amax=
adjustable
330° by steps of 30°
guard trac™
Short
Amin= 60° to Amax=
adjustable
330° by steps of 30°
guard trac™
7.3.2. End barrier
The double bracket of the end barrier is ballasted
by 4 counterweights (fg.14 position b).
A counterweight interface (rep.1 fg.20) should be
placed
between
each
counterweight to ensure securing of the upper
counterweight
in
relation
counterweight (fg.20)
To
place
the
After
placing
the
lower
and
upper
to
the
lower

Publicidad

loading

Productos relacionados para Tractel guard trac

Este manual también es adecuado para:

Guard trac plus