Step 2: Closing Up The Support Bracket; Step 3: Cabling Preparation - Bodet Style 5 Instrucciones De Instalación

Soporte suspendido
Tabla de contenido

Publicidad

Idiomas disponibles

Idiomas disponibles

Step 2: Closing up the support bracket

1) Route the power supply cable and synchronisation cable (for wired clocks) into the support
tube. This cable comes from the client installation (not supplied by Bodet).
2) Mount the bracket arm to the wall (see page 16 for screw hole distances).
3) Fit the spacers to one of the two bracket side plates using the
screws (ref.: 601070) through the holes located opposite the cut
out blanking plate.
Example showing the bracket side plate
for a flag-mounted installation:
NOTE: MAKE SURE YOU PLACE THE
SPACER FLATS PARALLEL TO THE
BRACKET ARM.
4) Fit bracket side plates 1 and 2 to the
bracket arm.
Using the two screws supplied, screw the
second side plate into the spacers on the
first.

Step 3: Cabling preparation

Single sided:
The cables are not supplied. The connections are to be made with the cables from the existing
installation (customer installation).
Double sided (for Style 5/7 only):
The mains power cables must have an insulating sheath of at least 0.4 mm thick to ensure a
re-enforced isolation with regard of the AFNOR or Impulse synchronisation cables. Suggested
cable U1000r2v 3G1.5.
Lever spring cage
terminals
200 mm
Wires stripped on 11mm inside the connector
EN
8 mm
7

Publicidad

Tabla de contenido
loading

Tabla de contenido