7. OPERATION TEST

7.1.

TEST PROCEDURES

1.
Make sure that both the liquid and gas valves are fully open. Make sure there
are no refrigerant leaks.
2.
Make sure that the electrical wiring of the indoor and outdoor units is
connected as shown in 'WIRING".
3.
Make sure that each terminal {L, N) is correctly connected to the mains.
4.
Turn on the air conditioner in cooling mode for 30 minutes or more.
7.2.
EVALUATING PERFORMANCE
MODEL:
SERIAL NUMBER:
CUSTOMER NAME AND ADDRESS:
DATE:
Is the direction of rotation of the indoor unit fan correct?
Is the direction of rotation of the outdoor unit fan correct?
Can you hear any abnormal compressor noises?
Has the unit continued to run for at least 30 minutes?
Checking the temperature in the room:
In: BS___/BU___ ºC
Checking the outdoor temperature:
Out: BS___/BU___ºC
Checking the pressure:
Discharge pressure: Ps=___ Bar
lntake pressure: Pa=___Bar
Checking the voltage:
Rated voltage: ___V
Check the current reaching the compressor
Power consumption: ___kW
Current consumption: ___A
Is the refrigerant charge sufficient?
Are the devices for controlling operation working correctly?
Are the safety devices working correctly?
Has the unit been checked for refrigerant leaks?
Is the unit is clean both inside and outside?
Is all the equipment secured?
Is the equipment secured so that it does not make any noise?
Is the filter clean?
Is the heat exchanger clean?
Are the gas and liquid service valves open?
Does the waste water drain away without any problems?
27