Installation Procedures
The standard attached accessories of the units of this series refer to the packing; prepare other
accessories according to the requirements of the local installation point of our company.
There are two sets of pipes in the unit,please use branch pipe when installation,the spec is FQG-
B370,details plsase refer to the using guide of the Branch pipe.
1. Before installation [before finishing the installation, don't throw away the attached parts
required for the installation]
Determine the route to move the unit to the installation site;
Don't tear the package open before moving the unit to the installation site. When unpacking is
needed, a soft material or protector block with ropes can be used to lift the unit to avoid damaging
or scraping of the unit.
2. Select the installation site
(1) The installation site should be selected according the following conditions, which should be
approved by users.
where an ideal air distribution can be ensured;
where there is no blockage in the air passage;
where the condensed water can be drained out properly;
where the strength can bear the weight of the indoor unit;
where enough space can be ensured for maintenance. The outside air should be input from
the outdoor directly from the blast pipe. If the blast pipe can't be jointed, the air can't be input from
the suspended ceiling.
where the lengths of the piping between indoor units and outdoor units are within the allowable
range (refer to Installation of Outdoor Units)
where the distance of at least 1m between indoor units, outdoor units, mains supply, connecting
wires and television or radio should be kept as to avoid the image disturbance and noises of the
above electrical appliances. (Even if 1m can be ensured, noise might occur if there is strong
electric wave.) Additionally, equipments, television or other valuables can't be put under the unit
as to avoid the condensed water of the unit from dropping into the above articles, causing damaging.
(2) Height of Ceiling:The ceiling should be located at the place, where the central position
of air outlet port is less than 3m high above the ground.
(3) Hoisting studs should be used during installation. Check if the location can bear the weight
of the unit. Reinforce it before installation if necessary.
3. Preparation before Installation
(1)Please refer to the cooling system diagram of the unit
before installation,and connect the pipes according to the
diagram.
(2) Location relation between inspection hole on the ceiling
and the unit and the hoisting studs (unit: mm).
360
upside
1610
1525
1510
indoor heat exchanger
liquid
segregator
TC2
Ceiling
7
TC1
M
environmental
fan
temperature
electrical
expandtion
filter
filter
electrical
expandtion
over 100
air outlet port
air inlet port
gas pipe
tie in
liquid pipe
tie in
over 900