FR700V SERIES FUEL TRANSFER PUMPS
CAUTION! Threaded pipe joints and connections should be sealed with the appropriate sealant or sealant tape to minimize the possibility of leaks.
SKID TANK INSTALLATION
TYPICAL PEDESTAL / ISLAND INSTALLATION
PEDESTAL COUPLER
PEDESTAL PIPE
PEDESTAL BASE
FUEL TANK
1¼" SUCTION PIPE
Typical Skid Tank Installation
Materials
Installation Procedure
TANK ADAPTER
SKID TANK
Additional
specifications on page 7.
Typical "Island" Installation
Materials
Additional specifications
on page 7.
Installation Procedure
ELECTRICAL CONDUIT
CONCRETE ISLAND
36" SQUARE
3" MIN. OFF
TANK BOTTOM
• 1¼" pipe cut to a length that will extend to within 3" of the bottom of the tank
when screwed into the tank adapter with the tank adapter screwed into the tank
flange (see SKID TANK INSTALLATION diagram).
• Threaded pipe joint sealant appropriate for application.
• Anti-seize thread compound.
1. Thread the 1¼" pipe into the tank adapter. Seal threads liquid tight with
appropriate thread sealant.
2. Apply an anti-seize thread compound to the external threads on the bottom of
the bung adapter. Screw the tank adapter into the tank flange.
3. Mount the pump on the adapter; seal threads liquid tight with appropriate
thread sealant.
4. Fill-Rite recommends installation of an Anti-Siphon Device
(see page 5 for detailed information).
• 1¼" threaded suction pipe, cut to extend 32-1/2" above the island.
• FRPA125 Pedestal Kit (includes Pedestal Pipe, Base, & Coupler).
• Threaded pipe joint sealant appropriate for application.
1. Remove the coupler from the pedestal pipe by loosening the set screws.
2. Slip the pedestal pipe / pump base assembly over the 1¼" suction pipe.
3. Loosen the screws in the pump base to allow the pedestal pipe to slide down
exposing the end of the suction pipe.
4. Screw the coupler onto the suction pipe; seal threads liquid tight with
appropriate thread sealant.
5. Slide the pedestal pipe into the coupler and tighten the set screws.
6. Tighten the screws in the pump base.
7. Mount the pump on the coupler seal threads liquid tight with appropriate
thread sealant.
LAYOUT OF BASE ANCHOR BOLTS
1/2" BOLTS
1-7/8"
ELECTRICAL CONDUIT
CLEARANCE HOLE
7 25/32"
1-7/8"
PUMP FRONT