Getting around
3
Note:
The load bar foot plates have been locked in position for transportation and installation, and must be released
before weighing (see
Installing the load bars
4
Before you begin, ensure that the concrete pad is level.
1. Lift the crate so that the load bars can be positioned underneath. Align the holes of the crate and load bar mounting
plates and fix with 12 mm bolts at each load bar end.
Caution!
Dropping the crate with load bars fitted, or dropping the crate onto the load bars can damage the load bars.
2. Lower the crate/load bar assembly onto the concrete slab, ensuring that the load bar foot plates are not twisted or
binding in any way.
3. Fix each foot plate to the slab with a minimum of two 12 mm (½") masonry anchors (e.g. Dynabolt™).
Install the masonry anchors one at a time, using the clamping action of each anchor to restrain the foot plate for
subsequent drilling. Take care to ensure that the anchors do not force the foot plates sideways and cause
misalignment of the ball and cup loading system.
2
Installing the load bars
).