Lay a concrete foundation with buried anchoring brackets
and the base plate, making sure that it is pefectly level and
smooth, complying with the measurements show in figure.
If a concrete foundation is already available, secure the
base plate by means of appropriate dowels (not supplied)
so as to allow height adjustment.
Route the cable ducts through the right hole of the plate.
X+5 (*)
Ø8,5
40 (**)
Ø7
Ø50
min 60
(*) CROSSCRI
(*) CROSSCRP
(*) CROSSCRN2
(**) CROSS3TC
Note: if the cement area is already present, adjustable
SUPCS base can be used.
Attention: the gearmotor must be suitably raised from the
ground to avoid flooding.
3.3 Geared motor installation
-
Release the gearmotor and remove the key. Loosen the
two front screws and remove the casing.
-
Position the geared motor on to the base plate.
-
Gearmotor adjustments
Horizontally by sliding in the ancoring feet notches (max
5 mm).
Vertically with the [3] levelling screws [B] (max 10 mm).
Note: while adjusting vertically, keep the motor slightly
raised above the base plate so as to allow enough space to
secure the rack and to make any subsequent adjustments,
if necessary.
All manuals and user guides at all-guides.com
OPENING
Ø50
160
200
min 60
220
OPENING
X+5 (*)
Ø8,5
40 (**)
Ø7
160
200
220
X = 40
X = 30
X = 40
X
20
3.4 Rack installation
-
Release the gearmotor and set the gate in the open po-
sition. Place the rack on pinion [17] and move the gate
manually to secure the rack along its full length.
-
Once the rack has been secured, vertically adjust the
geared motor so as to have a gap of 2 to 3 mm between
the pinion and the rack.
Attention: the weight of the gate must not bear on the
pinion, otherwise malfunctioning will result.
-
Firmly secure the gearmotor with the nuts [A].
-
Slightly lubricate the rack and pinion after assembly.
Manually check that the gate slides evenly and without
friction.
13
A
±2,5
B
50
17
F
CROSS3E - IP1780