STARTING UP FOR THE FIRST TIME (after two hours)
Before activating the condenser unit:
- Make sure the remote mains switch QF1 is in the OFF position;
ON
OFF
- Remove the inspection panel;
- Remove the door of the electrical panel, setting QS1 to OFF
- Place the compressor thermal overload switch QM1 in
the ON position;
- Close the electrical panel door and fasten the screws
- Place the main switch QS of the appliance in the ON position
26
English 07/03
- Replace the inspection panel
- Place the main switch of the unit QF (outside of the unit)
in the "ON" position
ACTIVATING AND DEACTIVATING THE UNIT
- Place the remote switch SA1 (if present) in the ON position;
- Set the remote keyboard A6 (if present) to ON.
- The ACTIVATION and DEACTIVATION operations are
controlled by the combined HED SE or HEN S internal unit.
ON
OFF
To access the control panel, open the door:
- remove the screw 1;
- press the points (2) simultaneously and lift the door (3)
2
3
1
2
3
HCAT TE - HCAN TE