3.2
AC Wire Assembly and Connection
DANGER
Danger to Life due to High Voltages in the Inverter
Before connecting any electrical wires and components, please ensure the DC switch & AC circuit breaker are switched
OFF and cannot be reactivated.
Step 1
Approx. 45 mm
For "L" and "N"
Approx. 10 mm
4....6mm²
Approx. 50mm
For "PE"
Insert the conductor into a suitable
Insert the crimped conductors L, N and PE
ferrule acc. to DIN 46228-4 and crimp
into corresponding terminals and tighten the
screws (torque 1.4N·m)
Note: Please insure that the connector has been correctly installed!
3.3
DC Wire Assembly and Connection
Meeting the following requirements is mandatory. All warranty rights will otherwise be invalid.
3.3.1 Maximum open voltage of each string is less than 600V.
3.3.2 Maximum short circuit current of each PV input is less than inverter allowable limit.
3.3.3 The string is well insulated to ground in all cases.
3.3.4 Make sure that the DC connectors have the correct polarity.
3.3.5 If the PV connectors are not assembled properly and locked into place, arc or overheat may be induced.
Step 1
Step 2
Assemble the
7mm
Assemble the
7mm
Note: Don't crimp this part!
Step 4
Step 5
6
3.4
Wi-Fi/GPRS Connection (Optional)
The stick is included in the scope of delivery as an option.
3.4.1 Tighten the stick into the COM1 port. Make sure the stick is securely connected.
3.4.2 For the connection and configuration of the Wi-Fi stick please refer to <Wi-Fi stick User manual> .
Step 2
L
N
2
PE
Assemble the locking cap,
Screw the AC connector
threaded sleeve and swivel
firmly into the socket
nut together
Step 3
MC4
cable ends
Positive terminal
Assemble the connectors
Negative terminal
D4
cable ends
2.6-2.9 N·m
Positive terminal
Negative terminal
Crimp pliers to cable ends
Step 6
3.5
Smart Meter and DRED Connection
Step 1
Use a screwdriver (Tx25, torque:2.5 N·m) to
loosen the screws of the cover following the
indicated sequence (1~4)
3
Step 3
1
1
Please leave the screws on the holes
Step 3
Take the
2
sealing out
3
Remove one of the filler-plug
and keep the remaining in its
slot to prevent moisture from
enter
Step 5
For smart meter connection
METER
1
Positive
2
Negative
NOTICE
4.
Commissioning
Please check if
1. The inverter and mounting bracket have been correctly installed. 2. The inverter's exposed metal surface has a ground
connection. 3. The resistance between PV arrays and ground is greater than 1Mohm. 4. For any unused DC terminals,
there are DC connectors inserted to the terminal and sealed with waterproof caps. 5. The grid voltage at the point of
click
connection of the inverter is within the permitted range. 6. The AC circuit breaker must be correctly rated and wired. 7.
The cable communication connectors have been correctly wired and tightened.
Startup
click
Switch on the DC switch after finishing the above checks, then switch on the AC circuit breaker. When there is sufficient DC
power applied and the grid conditions are met, the inverter will start to operate automatically.
EAS ELECTRIC SMART TECHNOLOGY, S.L.
Address: P.I. Codonyers, C/Principal, 4 46220 Picassent (Valencia, SPAIN)
Carefully lift the cover for a vertical distance of approx. 80mm and
disconnect from power board
2
4
Approx.
80mm
Smart meter communication assembly
1
B
A
2
Unscrew
1
the nut
Route
4
the cable
Screwdriver Type: Blade 0.4 x 2.5
or
DRED terminal connection
DRED
DRED
1
2
For AS/NZS 4777, DRM0, DRM5, DRM6, DRM7, DRM8 are supported.
Make sure the cover and the communication cable gland has been mounted properly and adequately
Step 2
Step 4
or
DRED cable assembly
Pin1:DRM1/5
Pin5:RefGen
Rj45 Plug
Pin6:Com/DRM0
Pin2:DRM2/6
Pin3:DRM3/7
Pin7:N/A
Pin4:DRM4/8
Pin8:N/A
1 23456 7 8
Rj45 Plug
Step 6
Tighten the screws on the cover following
the indicated sequence (1~4).
(Tx25, torque:2.5 N·m)
2
3
4
1
Firmly secure cable gland by using a torque
of 2.5 to 3N·m to tighten the swivel nut
www.easelectric.es

Publicidad

loading

Este manual también es adecuado para:

Einsolar6.5v