Installation of the stove
The installation wall must be level. The stove must only
be mounted on walls with sufficient load-bearing ca-
pacity.
Attention: Mounting the stove directly on the modu-
lar chimney block of the chimney system is prohibited.
You must ensure that the fastening material is suit-
able for the building material of the mounting wall.
For building materials that are commonly used, such
as vertical coring brick or solid brick, we recommend
the following fastening system, for example, from the
company, Fischer:
– Injection anchor sleeves – plastic FIS H 16x85 K
– Anchor rod FIS A M10x110
– Injection mortar FIS V
Because the wall temperature can be as high as 85°C,
you must ensure that the fastening system is perma-
nently suitable for this temperature.
The permanent fastening of the device on the mounting
wall, is solely the responsibility of the specialised exe-
cuting company.
If the floor or carpet is flammable a stable, heat-re-
sistant spark protection plate must be used. This spark
protection plate must project beyond the combustion
chamber opening of the stove, 50 cm to the front and
30 cm to the side.
Installation sequence
Because the cover hood must be dismounted for instal-
lation of the side cladding and the OEC (instructions
are included in the respective packaging units), and for
changing the connection of the connection duct, the
cover hood should only be remounted after all attach-
ment parts are attached.
● The wall bracket is delivered mounted on the stove.
For mounting on the wall dismount the wall bracket
from the device. To do this, unscrew the 4 M12 fas-
tening nuts and pull the wall bracket out of the device
from the rear (see Fig. 5).
● Unscrew cover hood front and rear and take it off
(see Fig. 2 – 4).
● The connection of the stove pipe Ø 150 mm can be
executed either on top or on the rear. The device is
delivered pre-assembled for the top connection. For
this, break the cover on top out of the cover hood.
If it should be connected at the rear, then it must re-
mounted in the following steps:
– Completely break out or saw out the rear cover
from the cover hood. The support surface of the
cover hood must also be removed in this area.
– The connection duct Ø 150 mm, 140 mm long for
connection at the rear is in the combustion cham-
ber.
– Swap the sealing cover on the heating gas dome
from rear to top.
● Prepare the wall bracket for the rear stove pipe con-
nection as follows:
– Detach the thermal insulation in the area of the
cover for the rear wall connection from the brackets
14
Fig. 2
Fig. 3
Fig. 4
Sensor pocket
for temperature