1.
Place the energy meter provided after the mains supply and before the split power
downstream of the protection devices (MCB, RCD). Follow the diagrams below for
three-phase electrical connection:
2.
Feed the communication cables with suggested section of 0.5 mm
sheath (C)
3.
Follow the manual of the energy meter included in the wallbox package to connect the
communication cables (of an appropriate length) to RS485 output port CN12 'push-in'
spring clamps, without using tools.
4.
Use the following order for connection: starting from left, connect:
GND
RS485-B
RS485-A
5.
As indicated in the energy meter manual, when powering up for the first time, enter
the following settings:
Device address: 1
Bits per second: 38400 bit/s
Parity: Even
Stop bit: 1
Connection mode: 3L+N "Arithmetic"
The equipment can only be powered up once this step has been completed.
Failure to comply with these instructions can lead to serious damage to persons and
property, including death.