3. Test area
The DT70KV dielectric tester generates high energy loads to perform the
dielectric tests. This generated energy is very dangerous and for that
reason it is of extreme importance the correct preparation of the area
where the dielectric tester will be used.
There are 3 basic safety conditions of the test area:
• Grounding
• Distance
• Containment
3.1. Grounding
Correct grounding of the dielectric tester and test object is essential not
only for the safety of the operator, but also for the proper functioning of
the dielectric tester.
3.2. Distance
Keep the generating unit (high voltage) and the test object at a minimum
distance of 2 meters from the Control Unit.
3.3. Containment
Maintain a minimum distance of 2 meters between the Generating Unit
(high voltage) together with the test object, of all supposedly conductive
materials to avoid leakage of electric current.
Make sure that there are no explosive materials in the testing area.
In accordance with current safety standards, the surroundings of the
dielectric test area must be isolated and signaled to inhibit the approach
of third parties during the tests.