Checks before commissioning
8
Checks before commissioning
Once mounting and installation of the nBox system is complete, ensure that the following checks are performed in
accordance with HD 60364-6 Section 61 before commissioning is started:
1. Inspect the permanent electrical system.
2. Test and measure the continuity of the conductors.
3. Test and measure the insulation resistance of the electrical system.
4. Test and measure the protection provided by automatic switch-off of the power supply (check upstream fuses).
5. Test and measure the voltage polarity.
If an error is identified during testing and measurement, proceed as follows:
1. Rectify the error.
2. Repeat the checks (including any previously performed checks that may have been influenced by the error).
Checks before commissioning
Done
14
nBox, Quick commissioning 2.0 | 07.2022 | en