Controls; Operation; Automatic Operation Sequence; Setting Exercise Timer - Briggs & Stratton 35000 Serie Manual De Instrucciones

Tabla de contenido

Publicidad

Controls

See the operator's manual for complete descriptions of the
generator controls.

Operation

Automatic Operation Sequence

The generator's control panel houses a logic control circuit
board. This control board constantly monitors utility power
source voltage. Should that voltage drop below a preset
level, control board action will signal the engine to crank
and start.
When utility source voltage is restored above a preset
voltage level, the engine is signaled to shut down.
The actual system operation is not adjustable and is
sequenced by sensors and timers on the control board,
as follows:
Utility Voltage Dropout Sensor
• This sensor monitors utility source voltage.
• If utility source voltage drops below about 70 percent
of the nominal supply voltage, the sensor energizes
a 10 second timer. The timer is used to 'sense'
brown-outs.
• Once the timer has expired, the engine will crank
and start.
Utility Voltage Pickup Sensor
This sensor monitors utility power supply voltage. When that
voltage is restored above 80 percent of the nominal source
voltage, a time delay starts timing and the engine will go to
engine cool-down.
Engine Cool-down Timer
• When the load is transferred back to the utility power
source, the engine cool-down timer starts timing.
• The timer will run for about one minute, then the
generator will stop.
• Minimum engine run time is 5 minutes.
22

Setting Exercise Timer

It is recommended to have the generator go through an
excercise cycle once every seven days. During this exercise
period, the unit runs for approximately 20 minutes and then
shuts down.
Refer to the Control Panel Application Guide supplied with
this generator for more detailed information on the exercise
timer.
OR, refer to the Automatic Transfer Switch Application Guide
for more detailed information on the exercise timer.

Installation Inspection

Before placing the generator system into service, inspect the
entire installation carefully.
This completes the installation and start-up instructions.
The operator's manual provides full details on Operation,
Maintenance and Troubleshooting for this generator system.