7.4
Mounting the barrier (casing)
Note: 2 people required! The necessary parts can be found in the accessory package included in
the delivery contents of the barrier.
2x U-profiles
4x composite anchors Ø20mm x 110mm long
• Indicate drillings for composite anchors and prebore
• Position barrier and tighten screws slightly
• With barriers up to a length of 4m the final alignment can be executed after mounting the barrier
pole
• With barriers longer than 4m the alignment must be executed immediately (without barrier
pole) and the screws are tightened firmly
ATTENTION: It is important that the composite anchors are fitted well in order to prevent barrier
from becoming dislodged. Especially in case of long barrier poles this can be dangerous!
• The gap between the base of the barrier casing and the pedestal has to be grouted with silicone
to prevent moisture from entering (important for protection against corrosion).
7.5
Mounting the tip support post (support)
Mounting the pole strut should be done after barrier pole has been fitted and aligned.
Installation is executed by means of composite anchors (not included in delivery) in the
ground and on a solid and stable subsoil.
A pendulum support is available as accessory.
7.6
Mounting the barrier pole (straight)
Attention: 2 people required to secure barrier pole.
Barrier must be in "Closed" position. Barrier pole is slid onto attachment and fixed in place by
means of the cover plate and the two provided screws (accessory package barrier). The nut must
be put on from the outside resp. the screw is to be slid through from the inside out. The barrier
pole has to have a firm fit on the arm and must not move nor have any clearance. The screws
allow tightening. If the screws appear to be too short to begin with, omit the washer and/or the
circlip. After tightening both screws slightly, loosen one screw and remove it in order to provide
washer and circlip. Tighten screw again and now retrofit other screw.
20/40
BARS = 2x
BARM = 2x
BARL = 4x
Notes