Perform Safety Checks; Mount Covers - Eaton xChargeIn Manual De Instalación

Ocultar thumbs Ver también para xChargeIn:
Tabla de contenido

Publicidad

Idiomas disponibles
  • MX

Idiomas disponibles

  • MEXICANO, página 249
Commissioning
9.2

Perform safety checks

Before the initial use, check the effectiveness of the safety measure(s) of the
system according to the nationally applicable regulations.
Electrical systems or devices must be checked by the installer of the system
or device before the initial operation. This also applies for the expansion or
modification of existing systems or electrical devices. It is essential that all
conditions for the safety measures are observed.
Moreover, the following points are to be taken into account:
9.3

Mount covers

In order to operate the charging station correctly, all covers must be inserted
and screwed tight. If necessary, a seal can be attached.
To mount all covers, proceed as follows:
1) Insert terminal cover and tighten with 2 screws.
2) Insert connection panel cover and tighten with 4 screws with 2 Nm. The
46
The checks (continuity of the connections of the protective conductor, in-
sulation resistance, RCD (FI) triggering current, triggering time,...) are to
be performed.
The measurement devices must comply with the national regulations!
The measurement results are to be documented. A test report is to be
created and saved before the check.
If necessary, the right upper screw can be provided with the supplied
sealing cap (see
9.4 Attach
tabs on the connection panel cover must be flush with the enclosing
housing. Only then will the device be properly sealed.
If necessary, the right upper screw can be provided with the supplied
sealing cap (see
9.4 Attach
seal).
seal).
xChargeIn
Installation manual V1.01
© EATON

Publicidad

Tabla de contenido

Solución de problemas

loading

Tabla de contenido