7.8
CHECKS AND INSPECTIONS
7.8.1 MECHANICAL CHECKS
grease sliding seats of blocks placed under platforms and on bases;
lift fixing to the ground with 8 anchor bolts (min. recommended size ø = 16 mm)
clean all parts of the machine;
7.8.2 ELECTRICAL CHECKS
connections as per diagrams;
lift grounding;
7.8.3 HYDRAULIC SYSTEM CHECK
proper oil level in the tank;
no leakage and blow-by,
cylinder operation
7.9
SET UP AND ADJUSTMENTS
7.9.1 LOAD LESS CHECK
Carry out two or three complete cycles of lowering and lifting and check:
the lift for reaching its maximum height;
the max height limit switch for proper operation;
the horn/signaling light for proper operation during the final travel;
7.9.2 CHECK WITH LOAD
Repeat checks provided for by 7.9.1 section with the vehicle loaded;
In this case some irregularities can occur; so considering that all adjustments shown are factory-
made, the following can be carried out as an exception:
7.9.3 BOLTS AND NUTS CHECK
After carrying out the checks with load, make a visual inspection of the machine and check bolts
and nuts for proper tightening.
68
WARNING: please follow carefully the
instructions in the coming paragraph for
avoiding damages on the lift.