7 Commissioning

7
Commissioning
7.1

Commissioning Procedure

This section describes the commissioning procedure and gives an overview of the steps you must
perform in the prescribed order.
Procedure
1.
Commission the inverter.
2.
Establish a connection to the user interface of the inverter.
There are various connection options to choose from for
this:
• Direct connection via WLAN
• Direct connection via Ethernet
• Connection via WLAN in the local network
• Connection via Ethernet in the local network
3.
Log into the user interface.
4.
Select the inverter configuration option. Please note that
the SMA Grid Guard code for changing the grid-relevant
parameters must be available after completion of the first
ten feed-in hours or installation assistant (see "Application
for the SMA Grid Guard code" available at www.SMA-
Solar.com).
5.
Ensure that the country data set has been configured cor-
rectly.
6.
Make further inverter settings as needed.
7.2

Commissioning the Inverter

Danger to life due to fire or explosion when batteries are fully discharged
A fire may occur due to incorrect charging of fully discharged batteries. This can result in death
or serious injury.
• Before commissioning the system, verify that the battery is not fully discharged.
• Do not commission the system if the battery is fully discharged.
• If the battery is fully discharged, contact the battery manufacturer for further proceedings.
• Only charge fully discharged batteries as instructed by the battery manufacturer.
56
SBSxx-US-10-IA-xx-12
WARNING
SMA Solar Technology AG
See
see section 7.2, page 56
see section 7.3, page 58
see section 7.4, page 62
see section 7.5, page 63
Inverter user manual
Inverter user manual
Installation Manual

Publicidad

Tabla de contenido
loading

Este manual también es adecuado para:

Sunny boy storage 5.0-usSunny boy storage 6.0-us

Tabla de contenido