5  LCS-Tool
Figure 14: LCS-Tool - list of all inverters connected to the
Inverter Manager
12. If sufficient PV power is present and the grid code
conditions are met, the inverter starts the operation.
Figure 15: LCS-Tool - commissioning report
18
IMVIOBOX-IA-xx-14
SMA Solar Technology AG / SMA Solar Technology America LLC
13. During commissioning it is possible to download a
commissioning report in the Reports menu. The report
contains information about inverter settings, including
actual disconnection values for each inverter. By
clicking the folder icon in the menu Reports, it is
possible to open a folder for commissioning reports
(incl. grid code information) (see figure 15).