GENERAL SECURITY GUIDELINES

Danger of damages caused by the loads when falling!
Always work with extreme security measures and according to the principle of management of the crane.
Verify the appropriate level of wear of all the elements ( hook, shackle, rings, ropes of rope slings, cables, chains, etc)
Do not use the weighing hook when the safety catch is damaged or there isn't any safety catch.
Work at the appropriate speed
It is completely forbidden to let the load tilt or to let horizontal forces operate. Avoid any type of hit, torsion (twist) or oscilla-
tion( for example when the weighing hook is hanged in a diverted way)
Do not use the weighing hook for cargo transport
Do not linger or walk under suspended loads
Do not use in construction work
Always verify suspended load
Do not exceed the nominal load of the crane, the weighing hook and any other towing device of the load
During the weighing of dangerous substances ( for example fused masses, radioactive material) the rules referring to the
handling of dangerous substances must be respected.

3.1. HOW TO HANG THE WEIGHING HOOK OF THE CRANE

To obtain the correct results of weighing it is necessary to respect the following recommendations:
• Use only the devices to hang the load that ensure the suspension of the weighing hook by only one fastening point.
• Do not use devices which are too big to hand the load, devices which do not ensure the suspension of the weighing hook
by only one fastening point.
• Do not use multiple slings.
• Do not drag or move loads with the weighing hook.
• Do not drag the weighing hook horizontally

3.2 HOW TO LOAD THE WEIGHING HOOK

1. Place the weighing hook over the load
2. Lower the weighing hook until it is possible to hang the load on its hook. When
you reach the desired height, reduce the speed.
3. Place the load on the hook. Make sure that the safety catch has been closed
correctly.
If you place the load using sling ropes make sure that the sling is placed correctly
in the centre of the hook.
4. Upload the load slowly. If you place the load using sling ropes make sure that
the load is well-balanced and the sling is correctly placed.