6 TRUNK INSTALLATION
6.1.2 Attach the trunk cable to the vertical cable mesh using velcro tie wraps (Figure 23).
6.1.3 Organize and group the fiber trunks in bundles as they will be connected at each deck.
6.1.3.1 Positioning and routing cables that enter the frame entrance first will provide
the best bend radius control and utilization of the frame entrance point. (See
figure 19)
6.1.4 Mount each deck group into the cable clamp by removing the required rubber
grommet rings.
6.1.4.1 Secure each trunk at the heat shrink as shown in Figure 24.
6.1.4.2 Secure the clamp by tightening the wing nut. (DO NOT over-tighten or
change the physical characteristics of the cable jacket).
Figure 23
Figure 24
33
Secure Velcro
®
tie
wraps to the vertical
cable mesh at the
available lance points