Schüco IPE 2700 SN 05 Manual Del Usuario página 44

Tabla de contenido

Publicidad

Idiomas disponibles
  • MX

Idiomas disponibles

  • MEXICANO, página 53
Commissioning
Commissioning single unit
System with one inverter
Single device
40
NOTE
For a better understanding of keyboard operation, please also see the chapter Ope-
ration.
The procedure for commissioning the inverter as a
x single unit
x and as a master and slaves with several networked units
is described in detail below.
1.
The commissioning process starts with setting of the display language. Select
the language in selection menu with
Confirm the selected language with
2.
Select the country in the selection menu with
3.
Confirm the country of installation with
NOTE
The inverter only starts feeding current into the grid once the country has been se-
lected.
4.
Select "Single unit" in the selection menu with
Confirm with
.
5.
Set the date and time.
Select date with
. Change the selected number with
the next number with
Confirm the date with
/
.
.
/
.
/
/
.
and set the time accordingly.
.
.
/
and jump to
IPE 2700 - 5000 SN 05

Publicidad

Tabla de contenido
loading

Productos relacionados para Schüco IPE 2700 SN 05

Este manual también es adecuado para:

Ipe 3000 sn 05Ipe 3600 sn 05Ipe 4500 sn 05Ipe 5000 sn 05

Tabla de contenido