Commissioning - log (Example)
Mechanical Inspection of Low Voltage Switchboards
1. Data to identify the object inspected:
See rating plate located in the left-hand end cubicle of the switchboard, inside of the cubicle or upper compartment door.
Client
:
Location:
Country:
Switchboard or part:
Type:
Manufacturer ident. (factory) No.:...................................................
Rated operational voltage:
Rated short-time current:
2. Switchgear room:
Item No.
2.1
The room can be properly secured against unauthorized access (locked).
2.2
All necessary measures have been taken to ensure the room meets the
local safety standards.
(e.g. escape routes, emergency lighting, fire-fighting facilities, signs)
2.3
The ventilation and air extraction works.
(air-conditioning functions, ventilation slots not obstructed)
2.4
The means for transporting heavy switchgear / withdrawable units
provided in the specified quantity and in good condition.
2.5.1
The switchboard accessories are complete according to documentation
(e.g. double-bit key, fuse grip, lamp installer, operating tool for
withdrawable circuit breakers and withdrawable units).
2.5.2
The switchboard accessories are in good condition.
2.5.3
The switchboard accessories are stored in a suitable place (easy access,
neatly arranged, protected against damage and theft).
2.6.1
Grounding and short-circuiting devices are provided in the specified
quantity.
2.6.2
Grounding and short-circuiting devices match the ratings of the
switchboard and are sufficiently labeled.
2.7
Notices indicating the location of the switchboard documentation are
provided at visible positions in the switch room (e.g. where the tools are
kept).
3. Switchboard, General
Item No.
3.1
The switchboard documentation is complete, sorted and accessible at the
given location (e.g. operating instructions of switchboard and relevant
switchgear as well as updated device listings and circuit diagrams).
3.2.1
The designation of the switchboards is complete
(switchboard, cubicle and feeder designations).
3.2.2
All connectors, terminals, and other cable connection points are labeled
correctly and completely.
3.2.3
Marking of external cables is correct and complete (if required).
3.2.4
Equipment identifiers are complete.
3.2.5
Main busbar markings have been replaced if damaged.
(L1, L2, L3, N, PEN, L+, L-).
3.3
Insulation test has been performed. If R> 1000/V of the rated operational
voltage, faults have been tracked and eliminated.
8PQ9800-7AA73
....................................................
....................................................
....................................................
....................................................
....................................................
....................................................
....................................................
Commissioning Step Performed
Commissioning Step Performed
Log-No: ..........................
Room ident.: ..................
Yes
No
Remarks
Yes
No
Remarks
A1