System Setup (For Gc1031 Controller And Trcm Board); System Setup (For Standard Controller And Trcm Board); Supervisory Control Wiring (A-A) And (B-B) - Briggs & Stratton 071210 Manual Del Usuario

Tabla de contenido

Publicidad

Idiomas disponibles

Idiomas disponibles

System Setup (for GC1031 Controller
and TRCM Board)
1. No setup is necessary for the GC1031 controller to
function with the TRCM board.
System Setup (for Standard Controller
and TRCM Board)
This is only applicable to Briggs & Stratton generator
controller software version E1 or higher, hardware E4 or
higher. For system setup, refer to the flowchart (Figure 6) and
the steps that follow.
1. Go to the generator control panel.
NOTICE Make sure the generator controller is off.
2. Access the advanced menu screen settings. Refer to
the Control Panel section in the Generator Operator's
Manual.
3. In the advanced menu screen, scroll to the transfer switch
settings as shown in Figure 6.
4. Set the TRCM and push OK.
5. If the generator is installed in an area regularly subjected
to temperatures below 40°F (4°C), select a 50 second
warm up time at the advanced menu settings. The factory
default is set to a 20 second warm up.
6. Put the 15A ATO fuse into the fuse holder of the
generator controller.
7. Measure the voltage across the GND terminal and +12V
DC at the generator's electrical box. The voltage should
be approximately +12V DC. If there is no voltage, check
to make sure that the hardware revision of the control
panel is E4 or higher.
10
6
Supervisory Control Wiring (A-A) and   
(B-B)
• A-A and B-B are NC contacts that are used as lockouts
when the transfer switch is switched to generator power.
Note: A-A and B-B are independent circuits.
• A-A and B-B are rated 120V AC, 1A (Figure 7).